Reservoir Group’s On-Ice™ Half Mooncoring technology helped minimize core jamming and maximize core recovery in a new exploration well.

Customer Challenge: A large client in the U.A.E. conducted an exploration job that required cutting core in a highly interbedded heterogenous formation that was never cored before. While Schlumberger conducted the integrated operations, they looked to Reservoir Group to help maximize core recovery.

Reservoir Group Solution: With a three-week deadline, Reservoir Group along with Schlumberger’s IPM team studied the project and recommended using the 100 ft core barrel length accompanied with the On-Ice™ Half Moon Inner Tubes to minimize the risk of jamming in such heterogeneous formations and avoid damaging the expected soft layers in between relatively hard layers. The client agreed with our recommendation and provided full support to execute our On-Ice Half-moon jam prevention system.

Download the full success story.